Rough Order of Magnitude (ROM) Pricing, Long-Term Options, and Interim Planning

Board of Trustees | September 16, 2026

Download the presentation (PowerPoint) View the presentation (PDF) Download the NAC report (PDF)

Ramona Elementary School

Tonight’s update: Rough Order of Magnitude (ROM) pricing and options

1. Pricing

Review the repair ROM and what it means for the long-term decision.

2. Long-term choice

Compare repair and rebuild at a high level: cost, timing, and risk.

3. Interim planning

Identify a mid-term option that can work under either long-term path.

Ramona Elementary School

ROM pricing changes the decision context

Repair costs

ROM construction estimate$10.2M
Soft costs allowance$5M
DSA-triggered rehab / seismic$2.8M
Estimated total repair cost:$18M

Repair costs are at ~90%

DSA Formula Based Replacement Value

Ramona Elementary School

Repair path: mandatory rehabilitation scope

50% threshold: DSA rehabilitation evaluation adds scope beyond exterior repairs.

Structural / seismic systems

Diaphragms, bracing, collectors, connections, hold-downs, gravity loads and wind resistance.

Foundations and load path

Steel sill/C-channel, anchor bolts, post bases, foundations and module-to-module connections.

Nonstructural seismic bracing

Ceilings, lights, HVAC/ducts, piping, conduit, electrical, fire alarm and sprinkler supports.

Verification and certification

Material testing, destructive verification, peer review/geotech if needed, separate DSA certification.

Ramona Elementary School

Repair path: approximate timeline

  • 6 mo.Design
  • 6 mo.DSA review
  • 2 mo.Bid
  • 12 mo.Construction

Approximate total: 26 months

Schedule risk: DSA rehabilitation scope and concealed damage could extend the timeline.

Ramona Elementary School

Rebuild path: approximate timeline

  • 8–10 mo.Design
  • 6 mo.DSA review
  • 2 mo.Bid
  • 18–24 mo.Construction

Approximate total: 34–42 months

Rebuild takes longer, but avoids placing a near-replacement investment into aging modular buildings.

Ramona Elementary School

Long-term choice: repair or rebuild

Repair*

  • ~26 months
  • ~$18M+
  • Keeps aging modular buildings

Rebuild

  • ~34–42 months
  • $45M - $50M
  • New useful life

*Repair is unusual at this scale: major cost, DSA rehabilitation, and continued use of older modular buildings.

Ramona Elementary School

Interim planning works under either path

The District still needs a mid-term student-location strategy while repair or rebuild proceeds.

Option One

leave 2/3 at Rose Avenue (all Ramona students at Juanita except TK/K/2/3)

Timeline

  • Approximately 2-4 Years

Student Placement

  • TK/Kindergarten: Ramona Site
  • 1st: Juanita
  • 2nd-3rd: Rose Avenue
  • 4th-8th: Juanita

Total Enrollment by Site 27/28

  • Ramona: 160-170 (TK/K)
  • Rose Avenue: 541 (TK-5) — 165 Ramona Students (2nd/3rd)
  • Juanita: 760 (Grades 1-8)

Notes

  • Ramona site able to hold up to 7 TK/K classes with 4 additional portables (all Ramona and Juanita TK/K)
  • Ramona 2nd/3rd graders remain at Rose Avenue School
  • No impact on Frank School enrollment

Option Two

move 6-8 off Juanita site (utilizing Ramona for TK/K)

Timeline

  • Approximately 2-4 Years

Student Placement

  • TK/Kindergarten: Ramona Site
  • 1st-5th: Juanita
  • 6th-8th: Frank

Total Enrollment by Site

  • Ramona: 160-170 (TK/K)
  • Juanita: 703 (Grades 1-5)
  • Frank: 1167 — 225 Juanita 6th-8th students

Notes

  • Ramona site able to hold up to 7 TK/K classes with 4 additional portables
  • Ramona grades 1-5 all at Juanita
  • Frank School increases by approximately 225 students

Ramona Elementary School

TK/K portable option: timing and cost range

  • 2 mo.Design
  • 2 mo.DSA
  • 2 mo.Bid
  • 4 mo.Construct

Fall 2027 feasible if the District starts now.

Lease-based planning range: ~$2.2M to ~$4.1M

Purchase-based planning range: ~$2.7M to ~$4.6M

Option Three

no utilization of Ramona site (all Ramona students at Juanita except 2/3)

Timeline

  • Approximately 2-4 Years

Student Placement

  • K: Juanita
  • 1st: Juanita
  • 2nd-3rd: Rose Avenue
  • 4th-8th: Juanita

Total Enrollment by Site 27/28

  • Rose Avenue: 541 (TK-5) — 165 Ramona Students (2nd/3rd)
  • Juanita: 860 (Grades K-8)

Notes

  • Juanita limited to 4 total TK/K classes
  • Ramona 2nd/3rd graders remain at Rose Avenue School
  • No impact on Frank School enrollment
  • Impact on other sites that would need to add 3-4 TK/K classes

Option Four

Do not repair or rebuild.

Timeline

  • N/A

Student Placement

  • All students moved to other school sites within OSD

Total Enrollment by Site 27/28

  • TBD for other sites

Notes

  • Complete the process to re-boundary all school sites to incorporate Ramona students into other sites.
  • Impact to most/all OSD schools, as approximately 500 students would be placed at other sites.

Ramona Elementary School

Use Ramona campus for TK/K

Site plan of the Ramona campus bounded by Cooper Street to the north and Bonita Avenue to the west

Campus site plan. The buildings shown are listed below.

Shown in blue

  • Building 200
  • Building 300
  • Building 400
  • Building 500
  • Building 600
  • Building 800
  • Building 1000

Shown in orange

  • Building 1100
  • Building 1200
  • Building 1300
  • Portable
  • Four additional portable pads

Ramona Elementary School

Decisions ahead

1. Long-term: repair or rebuild
2. Mid-term: TK/K portable concept
3. Commitments: design, procurement, DSA, funding

The TK/K option can support either repair or rebuild.