Skip To Main Content

Ver esta página en español

Ramona ElementaryFacilities Update

Path of Travel, Division of the State Architect (DSA) Review, and Next Steps

September 2026

Current Status

Ramona students and staff remain temporarily relocated.

  • The District is maintaining school operations at receiving campuses.
  • Facilities, architects, engineers, and risk management staff continue to evaluate the Ramona campus.
  • No reopening date has been established while the repair approach is being developed.
  • Staff continues to address concerns raised to the board.

Actions Taken Following Relocation

As a result of the Ramona relocation, the District added staffing support and expanded communication with families.

10

additional campus assistants

Hired to strengthen supervision and support at welcoming schools.

Parent Meetings

  • July 30, 2026, 6:00 pm via Zoom
  • July 31, 2026, 9:00 am @ Juanita MPR
  • August 6, 2026, 6:00 pm via Zoom
  • August 25, 2026, 6:00 pm @ Juanita MPR

Held to provide updates, answer questions, and hear family concerns.

Continued focus

Supporting students and families while maintaining safe and orderly operations at welcoming schools.

Northwest Campus Access Update

A detailed site plan featuring various colored building blocks in the foreground and a white background with technical labels and a legend.
Proposed limited access path for the northwest portion of campus.

NAC is studying a limited access path for the northwest portion of campus.

  • Limited review from the Division of State Architect (DSA) is expected for accessibility, path of travel, fire alarm, fencing, and fire/life-safety items.
  • Use of this area remains contingent on review, verification, and any required corrections.

What Limited Division of State Architect (DSA) Review Means

Access

Path of travel and accessible features must be verified.

Fire/Life Safety

Fire alarm, fire access, and fencing impacts must be reviewed.

Structural

Certain site elements are exempt from structural review.

Looking Ahead

Next steps

  • Confirm the path of travel and required Division of the State Architect (DSA) review for the northwest campus area.
  • Architectural review of Rough Order of Magnitude (ROM) pricing.
  • Return with clearer repair options, cost information, and timeline implications.
  • Continue to support students and families.
Bottom line: No reopening date has been set. The District will return to the board with clearer repair options, cost information, and timeline implications as the DSA review and ROM pricing come in.

Oxnard School District · Ramona Elementary School